The Guangzhou Baijiang Subway Station Stereo Garage Project was launched in 2020
Guangzhou Baijiang Subway Station Project
Baijiang Subway Station is located at the junction of Guangzhou-Shenzhen Highway and Dongjiang Avenue. It has a good geographical location, surrounded by 6 large residential areas, and the commuting time from the subway to Zhujiang New Town is only 53 minutes. Many office workers who do not live near Baijiang Subway Station will also choose this station to commute, and even car owners from other towns will drive to this station for subway transfers. Before the construction of the Eounice Stereo Garage, the road surface in the station area had been in a state of random parking, causing many problems for urban management.
With its strong technical research and development capabilities and highly coordinated production and manufacturing strength, Olais designed a 5-story lifting and lateral shifting three-dimensional parking garage for the project, providing more than 300 parking spaces, helping to solve the problem of random parking around Baijiang Metro Station, effectively improving the traffic congestion on the road, and car owners can park with peace of mind without fear of being fined by the traffic police. Sufficient parking spaces and larger parking spaces greatly improve the parking experience of car owners and add more convenience.
eounice smart parking system
On-site picture of Eounice three-dimensional parking garage
Project highlights
5-floor lifting and lateral shifting
smart parking system
Larger car capacity
The project adopts a 5-story lifting and lateral shifting parking garage design, covering an area of 2,350 square meters and a total height of 10 meters. The project is equipped with a complete intelligent parking guidance system, which has increased to 308 parking spaces from the original 66 cars, an increase of 367%. The size of the parking space is 5300mm*2200mm*1850mm, covering more and more comprehensive models, which can effectively solve the problem of random parking caused by insufficient roadside parking spaces. The sufficient and considerate parking space design has also greatly improved the parking experience of car owners.
lift and transverse parking system
-Car pickup bell
-Eye-catching lighting design
There is also a car pickup bell in the project. When citizens need to pick up the car, they only need to press the bell and the staff will come to operate the car pickup. Thanks to the excellent dynamic line design in the project, only one staff member is needed to manage the entire project.
The exterior of the project is decorated with eye-catching lights, which can block wind, rain, dust and protect vehicles at ordinary times. It is a beautiful landscape at night.
-Real shots of the project site
The project was completed at the end of July 2020 and has been in operation for nearly 4 years. The average monthly insurance of vehicles is 220, accounting for 71.4% of the total number of parking spaces. The Olaisi three-dimensional parking garage has become the choice of many car owners. After the multi-story parking garage was completed and put into use, it helped solve the parking needs around Baijiang Metro Station, provided smoother and more convenient parking facilities, saved land resources, and greatly improved the parking and travel experience of car owners.